Building B - Project update  
 
Date: 13 to 17 - 02 - 2012 (Show room)
 
      

      

Building B Showroom
We are currently installing two new showrooms. One single bedroom showroom, and one double bedroom showroom.

 

Click photos
  Date: 13  to  17 - 02 - 2012
 
Project update - Building B      

Building B outside building
We have started installing concrete outer cladding, as in picture above. We have also started to install aluminum window framing, as to red arrow in picture above.

Building B inside
We are also currently progressing working in the Condo's, doing tiling in the bathrooms, and tiling in the toilets.

 

Click photos
  Date: 22-12-2011
 
      
Click photos
  Date: 22-12-2011

     

Updated picture building B. Plasterboard ceilings being installed on upper floors building B

 